The first Light Combat Aircraft Tejas Mk1A could finally be handed over to the Indian Air Force (IAF) early in 2027, possibly as soon as January, according to an exclusive report published by ThePrint on Friday, 13 November. The report, which cites a source familiar with the programme, says one or two jets could be delivered ahead of the Aero India 2027 show in Bengaluru if the schedule holds. Hindustan Aeronautics Limited (HAL), the Ministry of Defence and the IAF have not publicly confirmed a handover date.
What the report says
According to ThePrint, two requirements linked to the Mk1A remained pending, including one or two functions tied to the aircraft’s Israeli-origin radar. The report says the IAF may accept the first aircraft with some temporary concessions, to be closed out after delivery. The Week also carried the expected January timeline on the same day. A company source quoted by ThePrint declined to say when the jets would be handed over.
HAL decided in 2025 to fit the first batch of 83 Mk1A fighters with the ELTA EL/M-2052 AESA radar rather than DRDO’s indigenous Uttam radar, because certification of the Uttam was taking longer than planned. Integration of that radar with the electronic warfare suite, along with missile-firing trials and the weapons package, has been among the conditions the IAF set for accepting the aircraft.
A long-delayed programme
The Mk1A is years behind its original timeline. The contract for 83 aircraft signed in February 2021 called for the first jet to be delivered within three years. Several projected handover dates since then, including mid-2025 estimates, have passed without a delivery. The biggest single cause has been the late supply of General Electric F404-IN20 engines, which HAL ordered from the US company in 2021. Reports say HAL had received 14 engines by September 2026.
In September 2025, the Ministry of Defence signed a second contract with HAL for 97 more Mk1A fighters, made up of 68 single-seat jets and 29 twin-seat trainers, taking total Mk1A orders to 180 aircraft.
Why the timing matters to the IAF
The IAF’s fighter squadron strength remains well below its sanctioned level as older MiG-21 and other legacy types leave service, and the Mk1A is meant to fill much of that gap. Air Chief Marshal Ashutosh Dixit has said the force expects its first Mk1A squadron within the current financial year, which ends in March 2027, and has described the Tejas Mk1A, Mk2 and the AMCA programme as top priorities.
What to watch
A January handover would let HAL show a delivered Mk1A at Aero India 2027, but the date rests on unnamed sources and the programme has missed earlier targets. The pace at which GE engine deliveries arrive, and how quickly the outstanding radar functions are cleared, will decide whether the first squadron forms on the timeline the IAF leadership has set.